The Final Stages of Phase 1
This week has been mostly rain free and the team have been able to forge ahead.  The framework for the upper floor slab has been set and we are well advanced with the steelwork.  Roughing in for the plumbing and electrics will be done early next week and we should be able to cast the slab by Thursday if the weather holds.